|
CLICK
HERE TO VIEW! 
|
|
| |
Project:
SUNY ESF GATEWAY BUILDING
Owner: State
of New York
Client: SUNY Construction Fund
Completion Date: 2012
Construction Cost: $20 Million
Project Description:
Bryant Associates, PC is providing
the civil site design services for this project, Civil site design includes,
review and amending topographic survey, utility relocations, parking lot
relocation evaluation, emergency accesses, sidewalks, landscaping and
hardscapes, stormwater management & permitting, sewer, water and gas
service construction and relocation. This project has a LEED
Platinum goal. Bryant Associates, PC prepared all specifications
for the civil site portion of this project in MasterFormat™. Bryant
Associates, PC as a sub-consultant is responsible for drawing coordination
and control transfer from other disciplines such as MEP, Geotech &Structural.
This included coordination of demolition drawings utility relocation and
architectural foot-print which is critical to adjacent existing campus
structures for potential future connection. Bryant
designed this project utilizing a 3D model for
existing and proposed utilities, relocation and demolition
(Screen shots shown on lower left). Architectural
"Revit Foundations and Framing Incorporated in\to Real World Model.
Bryant also incorporated the shoring
and tie-back system into the model for conflict resolution and design
assistance.
Bryant is continuing to progress this model through construction to supply
the CM and Ccontractors with up to date site information. This project
is a NYS SUNY Construction Fund Project. Project procedures followed NYS
SUNY SUCF Program Directives.
View & Print
Project Sheet 
|
|
|
Existing View

|
Project:
Grand Ave (C.R. 39)
Location: Onondaga County, NY
Owner/Client: Onondaga County Department of Transportation (OCDOT)
Completion Date: 2009
Construction Cost:
$2.3 Million
Project Description:
As Prime Consultant, BRYANT ASSOCIATES performed the preliminary and final
design for the reconstruction of 2.7 km roadway reconstruction project.
Work included roadway reconstruction and overlay, new closed drainage
systems, a reconfigured/realigned 4-leg intersection with signalization
(shown in photo), utility relocations and two (2) large box culvert replacements.
The drainage and utility conflicts on this project were significant. Bryant
design and ROW survey and mapping, and developed design report. A complete
environmental screening was performed. In addition, stream realignment,
bank stabilization and fish habitat features where designed. Bryant developed
displays and gave the technical presentation at the Public Information
Meeting.
APWA
2008 “Transportation Project Of The Year” View
& Print Poster
View & Print
Project Sheet  |
Proposed
View |
| |
|
|
|
Project:
SUNY BROCKPORT - Special Events Recreation Center - SERC Phase 1 &
SERC Phase 2
Owner: State of New York
Client: SUNY Construction Fund
Completion Date: 2012
Construction Cost: $38 Million SERC
Phase 1 / $6
Million SERC
Phase 2
Project
Description: Phase 1
Bryant Associates provided civil site design services of this $32M+ college
recreational facility expansion project. Tasks included the civil site
design including, topographic survey, 900 space multipurpose parking lot
facility, emergency accesses, frontage roads and drop off centers, sidewalks,
loading dock access, structural design of retaining walls, landscaping
and hardscapes, stormwater management & permitting, sewer and water
service layout, demolition and utility relocations. The storm water management
included “Green” Infiltration Islands, Detention Ponds and
outfalls redistribution in order to alleviate an existing over taxed closed
drainage system. This project has a LEED
Platinum goal. Bryant Associates has investigated and
evaluated LEED items along with preparing all documentation related to
civil site LEED components.
View & Print Project
Sheet
~ Go to the Suny Brockport SERC Homepage
View the Construction Progress
Slideshow 
Project
Description: Phase 2
Under seperate contract from Phase 1, Bryant Associates was selected to
provided civil site design services of this $6M+ project. Tasks included
the civil site design including, topographic survey, drop off centers,
sidewalks, loading dock access, rain garden design & landscaping and
hardscapes, stormwater management & permitting, sewer and water service
layout, demolition and utility relocations. This project has a LEED Platinum
goal Associated with Phase 1. Bryant Associates has investigated and evaluated
LEED items along with preparing all documentation related to civil site
LEED components.
View & Print Project
Sheet 
|
|
|
Project:
Crouse Irving Memorial Hospital Surgical Expansion
Owner: Crouse Irving Memorial Hospital, Syracuse, New York
Client: Crouse Irving Memorial Hospital
Completion
Date: 2009
Construction Cost:
$50 Million
Project Description:
Bryant Associates provided design services to Crouse Memorial Hospital
for 4 projects related to the 3 story $50M+ hospital expansion project.
Design Services included, the main entrance and parking facility, city
roadway repair and reconstruction, landscaping, ADA compliant walkways,
sewer, water service design and stormwater design and compliance. Bryant
also provided Alternatives for a reconfiguration of the Emergency Room
Entrance and Ambulance Bays. Bryant Associates is also responsible for
the property & topographic and detailed vertical structural survey,
along with preparing base mapping and As-Built plans. Bryant Associates,
P.C. also supplied full specifications for all site components in CSI
Format. Of the projects five phases, three have construction.
Bryant Associates
has also performed civil site design services for a garage rehabilitation
project and three parking lot facility projects. Each parking facilities
consisted of over 200 spaces with Kard-Key access, lighting and “Blue-Light”
emergency service. Bryant provided Traffic studies, contract documents,
construction management and inspection services. Bryant Also prepared
and presented materials for City permitting and zoning variances.
View & Print Project
Sheet 
|
|
| |
Project:
Crouse Irving Memorial Hospital
Owner: Crouse Irving Memorial Hospital, Syracuse, New York
Client: Crouse Irving Memorial Hospital
Completion
Date: 2009
Construction Cost:
$400
Project
Description:
Bryant Associates performed civil site design services for a garage rehabilitation
project and three parking lot facility projects. Each parking facilities
consisted of over 200 spaces with Card-Key access, lighting and “Blue-Light”
emergency service. Bryant provided Traffic studies, contract documents,
construction management and inspection services. Underground stormwater
management systems were also designed on one of the lot expansion projects.
Bryant also prepared and presented materials for City permitting and zoning
variances.
View & Print Project
Sheet 
|
|
|
Project:
New York State Thruway Route 370 Traffic Impact Study
Owner: New York State Thruway Authority, Albany, New York
Client: New York State Thruway Authority
Completion
Date: 2009
Project
Description:
This project included a traffic impact study for the potential closure
of the Rte 370/I-90 overpass bridge in Liverpool New York. The project
area encompassed over 3 square miles, 13 intersections of which there
were 9 signalized. The village of Liverpool roadway configurations were
complex ranging from two- way local streets to 6 lane primary arterials.
Bryant developed complex "Trip Generation"
data to simulate detour conditions for the bridge closure. Traffic
data consisted of existing traffic data, traffic counts, projected counts
for construction year scenarios and detailed aerial mapping of commercial
and residential zones. Traffic modeling was performed with SYNCRO®
and consisted of emulating the existing conditions and detour condition
scenarios. The impact study addressed ingress/egress, saturation, LOS
changes along with travel time and speeds. Traffic signal data was both
gathered from municipalities and field generated. Bryant Associates would
like to thank all involved municipalities for their support.
View & Print Project
Sheet 
|
|
|
Existing View

|
Project:
Syracuse-Cedervale Road / Fay Road (C.R. 39)
Location: Onondaga County, NY
Owner/Client: Onondaga County Department of Transportation (OCDOT)
Completion Date: 2009
Construction Cost:
$1.5 Million
Project Description:
As Prime Consultant, BRYANT ASSOCIATES performed the preliminary and final
design for this 1.3 km roadway reconstruction project. Work included roadway
reconstruction and overlay, reconstructed shoulders, replacement of open
drainage systems, a reconfigured 5-leg intersection with signalization,
and utility relocations. Bryant performed the design, and ROW survey and
mapping, and developed the design report. A complete environmental screening
was performed, including the identification and removal of contaminated
materials. The project also included the reconstruction of 1000 meters
of Onondaga Boulevard. Bryant developed displays and gave the technical
presentation at the Public Information Meeting.
APWA
2006 “Transportation Project Of The Year” View
& Print Poster
View & Print
Project Sheet  |
Proposed
View |
| |
|
|
Existing View

|
Project:
Route 394 R&P
Location: U.S. Route 62toI-86 Steamburg, NY
Owner/Client: New York State Department of Transportation (Region
5)
Completion Date: 2000
Construction Cost:
$14 Million
Project Description:
This project included the resurfacing/reconstruction of NY Route 394 in
Chautauqua and Cattaraugus Counties. The project length was 22.5 km, and
the two-lane highway extended through two historic districts in the villages
of Randolph and East Randolph. The project also included three bridge
replacements and three major bridge rehabilitations. Major and complex
drainage improvements in the historic villages were also necessary. Bryant
Associates, P.C. generated visual simulations for 6 separate locations
through the historic areas.
View & Print Project
Sheet   |
Proposed
View |
|
|
|
Project:
U.S. Rte 7 Arterial Bennington Bypass
Owner/Client: Vermont Agency of Transportation
Completion Date: 1998
Construction Cost:
$45 Million
Project Description:
This VAOT project involved the construction of 5.5 miles of 4-lane VT
Route 7 on new location. The new highway would bypass the Town of Bennington,
VT. Two interchanges and 25 structures were also part of the project.
This project was located in an environmentally sensitive area, which resulted
in many bridge and culvert crossings over major streams. Close coordination
with various agencies and the public was required.
View & Print Project
Sheet  |
|
|
Project: Westmoreland
Tandem Trailer Facility (NYS Thruway Exit 32)
Location: Westmoreland, New York
Owner/Client: New York State Thruway Authority
Completion Date: 1998
Construction Cost:
$2.3 Million
Project Description:
This project involved the design of a truck tandem facility for the New
York State Thruway Authority, consisting of a 5 acre tandem parking lot,
toll plaza and Park-n-Ride expansion. The design included the tandem lot
layout, design of access ramps, toll lane and canopy extensions. Drainage
design also provided for a detention pond and an integral oil/water separator.
The project also included the analysis and design of an actuated interconnected
signal system.
View & Print Project
Sheet  |

|
|
Project:
New York State Thruway (I-90)
- West Bergen Road Bridge
Location: OverThe New York State ThruwayM.P. 380.57
Owner/Client: New York State Thruway Autority
Completion Date: (In Final Design Phase)
Construction Cost: $3,700,000
Project Description:
As Prime Consultant, Bryant performed preliminary and final highway and
bridge design including design survey and mapping.
The existing 4-span steel structure will be replaced with a 2-span continuous
weathering steel structure with integral abutments. This $3.7 million
project includes updating the survey and mapping, design report, foundation
design report, seismic design, approach roadway reconstruction, profile
modification, guide rail replacement, and the preliminary and final bridge
design.
View & Print Project
Sheet  |
|
| |
Project:
New York State Thruway (I-90) OverThe Mohawk River
Location: New
York State ThruwayM.P. 237.33
Owner/Client: New York State Thruway Autority
Completion Date: 2013
Construction Cost: $8,300,000
Project Description:
As Prime Consultant, Bryant performed preliminary and final highway and
bridge design including design survey and mapping.
The existing 380 ft. five-span haunched riveted painted steel plate girder
superstructure was replaced with a jointless three-span haunched continuous
weathering steel structure. Work included the addition of approach slabs,
substructure rehabilitation and modification, bearing design, scour protection,
closed drainage system design, wetland delineation, SPDES Phase II permits,
and Traffic Control with mainline crossovers. A steel bridge barrier system
(design service level TL-5) which allowed roadway drainage to pass under
the barrier system eliminated the need for scuppers.
View & Print Project Sheet
|
|
|
Project:
Middlebury Bridge No. 5
Location: Main Street (C.R. 7) over Oatka Creek
Owner/Client: Wyoming County Department of Highways
Completion Date: 2003
Construction Cost: $640,000
Project Description:
Bryant Associates, P.C. provided services for Preliminary through Final
Design (Phases I-VI) for the replacement of the existing single span steel
multi-girder bridge with a prestressed adjacent box beam structure with
integral abutments. The approach work included both vertical and horizontal
alignment modifications to limit adjacent wetland impacts and meet current
design standards. Also included were survey and mapping, ROW, hydraulic
analysis, foundation analysis, environmental permits, utility relocations,
and construction inspection services. Construction of this project was
funded through the Federal-aid transportation program, as authorized by
the Transportation Equity Act for the 21st Century (TEA-21).
|
|
|
Project:
Bellamy Harbor Park Pedestrian and Bicycle Bridge
Location: Rome, NY
Owner: City of Rome
Client: New York State Thruway Authority
Completion Date: 2001
Construction Cost: $890,000
Project Description:
This project was designed by Bryant Associates, P.C. under contract with
the New York State Thruway Authority in coordination with the NYSDOT and
the City of Rome. This structure is owned by the City of Rome and spans
the Mohawk River where the river meets the Erie Canal. The 70 meter (230
ft.) single span weathering steel bridge carries pedestrian and bicycle
traffic out of Bellamy Harbor Park toward the Fort Stanwix National Monument.
The abutments of the original truss vehicle bridge were modified and rehabilitated
to support the new pedestrian structure. Site lighting, concrete pavers,
railings, and landscaping were an integral part of this contract.
View & Print Project
Sheet  |
|
|
Project:
Gravel Road Bridgeoverthe NYS Thruway@ M.P. 317.46
Owner/Client: New York State Thruway Authority
Completion Date: 1998
Construction Cost: $1,000,000
Project Description:
Bryant Associates, P.C. was responsible for the preliminary and final
design of a new two-span continuous weathering steel multi-girder structure,
which replaced the existing four-span bridge. The completed contract plans
were included with plans developed by New York State Thruway Authority
for the replacement of four other overpass bridges in Seneca County. Bryant
performed a foundation analysis for all five bridge replacement sites.
View & Print Project
Sheet  |
|
|
Project:
Weedsport Interchange Bridge (NYS Thruway Exit 40)
Location: Weedsport, NY
Owner/Client: New York State Thruway Authority
Completion Date: 2003
Construction Cost: $2.4 Million
Project Description:
This project replaced the original 1953 four span steel multi-girder bridge
with a two span continuous weathering steel structure.
Bryant Associates, P.C.'s Scope:
Bryant Associates, P.C.provbided the
survey and mapping, design report, foundation design report, and the preliminary
and final bridge design for this project. The structure was replaced using
staged construction utilizing temporary traffic signalization. Also included
were the seismic design, approach roadway reconstruction, profile modification,
approach guide railing replacement, and the addition of a median barrier.
The New York State Thruway Authority included exit ramp and toll area
paving work with this bridge replacement contract.
View & Print Project
Sheet  |
|
|
Project:
Pump Station and Electrical Room Design for the Metropolitan Wastewater
Treatment Plant
Location: Syracuse, NY
Owner/Client: Onondaga County Department of Water Environment
Protection
Completion Date: 2003
Project Description:
As part of the Syracuse Metropolitan Wastewater Treatment upgrade
project, Bryant Associates, P.C. provided structural design and construction
details for the secondary effluent pump station and adjacent electrical
room. The pump stationhouses four 40,000 pound vertical pumps. Large roof
hatches were placed above the pumps to allow for their future removal
and replacement. Work at the plant also included the design and details
for pile support of the 72 inch secondary effluent force main and 84 inch
effluent outfall pipe with connection details to the existing outfall.
|
|
|
Project:
Harbor Brook Floatables Control Facilities
Location: Syracuse, NY
Owner/Client: Onondaga County Department of Water Environment
Protection
Completion Date: 2002
Construction Cost: $350,000
Project Description:
Structural design and detailing for the floatable net bag unit,
concrete anchorage and galvanized steel walkway structure. A stainless
steel bar rack attached to the walkway structure was designed to collect
large debris under high flow conditions and protect the net bag floatable
structure. Site work included access road improvements which consisted
of reconstruction and expansion of the existing access road, paved entrance
with new drop curbing and sliding security gate.
|
|
|
Project:
Ashford Culvert No. 23
Location: Cattaraugus County, NY
Owner/Client: Cattaraugus County Department of Public Works
Completion Date: 1997
Construction Cost: $140,000
Project Description:
This project included the preparation of PS&E documents for the rehabilitation
of a 96-inch diameter steel plate pipe using a slip-line procedure. The
existing pipe was lined with a polyethylene pipe and grout was pumped
in the void between the two pipes. The grout was also used to fill the
erosion caused by holes in the existing structure. BAPC also provided
survey and construction inspection services for this project.
|
|
|
Project:
Emergency Scour Repairs
Owner/Client: Wyoming County Department of Highways
Project Description:
Bryant Associates, P.C. was engaged by the Wyoming County Highway Department
to inspect three bridge structures, devise procedures for repair, prepare
repair plans and environmental permits, and perform the field inspection.
On July 8, 1998, several County owned bridges experienced severe scour
damage caused by flooding. Due to the severity of the damage, the NYSDOT
red-flagged and closed Sheldon Bridge No. 18, Bennington Bridge No. 8,
and Arcade Bridge No. 3. Due to the difficulty in accessing many of the
voided areas, various repair procedures utilizing grout filled bags and
pumpable concrete were developed. Stone fill was placed to provide for
future scour protection. These structures were reopened to traffic within
six to eight weeks after the flood.
View & Print Project
Sheet  |
 |
|
Project:
TOWN OF CICERO - Engineering & Construction Inspection Services
Owner/Client: Town
of Cicero
Completion Date: 2010 ~ Present
Construction Cost: Multi-Million Dollar Development Projects
Project Description:
As the Town of Cicero "Alternate Engineers", Bryant
Associates, P.C. provided the Engineering Review and Construction Inspections
Services beginning in January 2010. Bryant provided the review for the
design of the infrastructure and roadway Contract Plans for the Wallington
Meadows" and "Hancock Airpark" private developments. Review
also included SWPPP and Erosion & Sediment Control design and compliance.
Bryant Associates provided an Engineering Representative and and full-time
on-site Construction Inspector for all phases of these projects. Bryant
provided material and submittal approvals as well as field verification
of products, documentation and testing oversight and field change orders.
Bryant's personnel followed Federal "Murk" documentation procedures
throughout the contracts which spanned multiple seasons.
|
|
|
Project:
I-490/I-590 Interchange Reconstruction (CAN OF WORMS)
Owner/Client: New York State Department of Transportation
Completion Date: 1992
Construction Cost: $123 Million
Project Description:
Bryant Associates, P.C. performed inspection of the miscellaneous construction
operations consisting of all utility work, retaining/sound walls, signing,
pavement markings, sidewalks, fencing and landscaping. Bryant Associates,
P.C. was also responsible for inspection of the installation of all closed
drainage storm water sewers and sanitary sewers as well as the installation
of all lighting and traffic signalization systems.
View & Print Project
Sheet  |
|
|
Project:
Bridenbaker Creek Culvert Rehabilitation @ M.P. 225.45
Owner/Client: New
York State Thruway Authority
Completion Date: 2001
Construction Cost: $250,000
Project Description:
Bryant Associates, P.C. provided the construction inspection on this double
barreled box culvert on Bridenbaker Creek. The construction included major
repair to the interior and exterior of the culvert with cast-in-place
concrete, as well as channel modification with erosion control measures.
View & Print Project
Sheet  |
|
| |
Project:
Metropolitan Wastewater Treatment Plant
Location: Syracuse, NY
Owner/Client: Onondaga County Department of Water Environment
Protection
Completion Date: 2001
Construction Cost: $25,000,000
Project Description:
In addition to Bryant Associates, P.C.’s involvement in the structural
design of this innovative ammonia and phosphorous removal facility addition
to the treatment plant, construction inspection services were also provided.
BAPC provided inspectors for both the pile driving operations and for
inspection of the civil/structural work during plant construction.
View & Print Project
Sheet 
|
| 
|
|
Project:
Metropolitan Wastewater Treatment Plant Survey
Location: Syracuse, NY
Owner/Client: Onondaga County Department of Water Environment
Protection
Date of Survey: 2001
Project Description:
Bryant Associates, P.C. performed the field survey and base mapping for
the design and upgrade of the $100 million Syracuse Metropolitan Wastewater
Treatment Plant. Critical plant elevations were measured for use in preparing
a hydraulic profile of the existing plant. The topographic survey located
physical features such as roads, signs, lights, manholes, catch basins,
along with buried and above ground utilities.
|
|
|
Project:
Five Bridges on Route 3
Owner/Client: New York State Department of Transportation
Date of Survey: 2000
Project Description:
Bryant Associates, P.C. performed the design survey and mapping for five
bridges on NY Route 3 in Oswego County. Channel survey was also performed
for all five bridges, which was used to generate HEC-RAS water surface
profiles and channel sections.
The channel overbanks were very flat, and required extra wide sections
for proper backwater modeling. Bryant recommended the use of GPS instead
of traditional survey methods, which ultimately saved the client $40,000
in survey fees.
|
|
|
Project:
Caughdenoy Dam Survey
Location: Caughdenoy, New York
Owner/Client: New York State Canal Corporation
Date of Survey: 1998
Project Description:
Bryant Associates, P.C. performed a topographic and hydrographic survey
for an area 400 feet downstream and 2200 feet upstream of the dam. Subsurface
elevations were measured using electronically recorded soundings and GPS
technology. Over 1800 subsurface elevations were measured in four hours
using this technology. These measurements were later confirmed using conventional
sounding equipment. The soundings were taken in the backwater above the
dam, along an old canal and within a marina. Bryant Associates, P.C. was
able to provide the New York Canal Corporation with a very accurate map
showing the bottom contours of the area at a low cost.
View & Print Project
Sheet  |